28 Jan

Location: Blythe, CA

Timeline: May 2019 to July 2019

Construction Methods: Installation of Steel Pipe

SCOPE:
– Fabricate 1.5”, 8”, and 10” steel piping – approx. 3,500 ft
– Excavate install 4” PVC piping and retention basin
– Excavate install 800’ of 2” sump discharge piping
– Excavate install 80’ of 8” water line loop to firewater loop
– Backfill excavations once piping is installed and inspected
– Hydro test system
– Tie-in system
– Over-excavate for pipe supports backfill w/ 2-sack slurry
– Form pour (13) pipe supports foundations for piping
– Fabricate steel for pipe supports install
– Coat and paint piping once complete
– Assist electrical contractors with excavation of conduit supports
– Assist with commissioning of system